So, the new facility is 105,000 ft^2, plus offices.
We need 102,000 ft^2 plus offices.
I have just been told that to help recoup expenses, we will be leasing 25,000 ft^2 out for storage to another firm. Also, the floor plan we developed based on available utilities and scrubbers has been scrubbed, and the layout will be decided on by everyone except facilities and engineering. Marketing, for example, has some good ideas about machine tool placement.
This will cost about $759,000 in additional electrical work, plus another $80,000 in permit changes, not to mention the permanent loss of revenue due to decreased efficiency of the production lines (which are more "weird figure 8s" than "lines".)
We now have 422 days total (293 regular workdays) to complete this move. The machine tools will now take 450 days to move, assuming we want to keep production going during the move.
I should have gone to Wyoming, really.